Hickson Road remediation

The remediation project on Hickson Road is progressing well and work will soon commence to relocate the remediation tent north of its current location.

In order for this work to take place, a temporary lane closure of the northbound lane of Hickson Road, opposite 30 to 38 Hickson Road, will need to occur.

Traffic management will be in place throughout this work to maintain vehicular access on Hickson Road at all times.

The northbound lane closures are expected to take place during the times below:

  • 18 June 2018 to 1 August 2018
    • Monday to Friday: 10am – 3pm
    • Saturday: 7am – 5pm

Barangaroo Site

As part of the remediation project on the Barangaroo site, additional equipment will need to be delivered for the construction of the remediation tents required for the next phase of work.

Pending final approval, this work will take place on Saturday, 2 June 2018 and Saturday, 16 June between 7am and 5pm.

A small crane will be used in Watermans Quay to lift the equipment onto site. To protect the safety of road users, pedestrians and our workers, it is necessary to temporarily close a section of Watermans Quay and Barangaroo Avenue to carry out this work.

Barangaroo Avenue will be closed to traffic from Lime Street for the duration of the work, however vehicle access to the International Towers Sydney basement and resident parking will be maintained at all times.

Pedestrian access to the shops, restaurants and cafes will be maintained as usual. 

Vehicles requiring access to the International Towers Sydney loading dock will need to enter Watermans Quay via Hickson Road.

Please see community notification for more information and maps.

 