Hickson Road Upgrade - Stage 4 work - 23 June 2018

As part of the Barangaroo development an upgrade of Hickson Road, between Watermans Quay and the Sussex Street Bridge, is currently being delivered. The third stage of this work on the eastern side of Hickson Road will soon be completed and planning for the fourth and final stage of work has begun.

The final stage will commence on Saturday, 23 June 2018 and involves the construction of the median strip and tree planting in the middle of the road, south of the Hickson Road and Napoleon Street intersection. Work is expected to be completed in late August 2018.

As part of this stage of work, a temporary construction compound will be established in the middle of the road on Saturday, 23 June from 7.00am to 5.00pm and on Sunday, 24 June 2018 from 8.00am to 5.00pm.

Please see community notification for more information 

 