Barangaroo Remediation - Hickson Road Night Work - 15 July 2018

The remediation project on Hickson Road is progressing well. The large remediation tent is currently being moved north to continue the remediation of the western side of the road.

As part of this project we are required to undertake some underground sewer repair work during July. As is common with work on utilities, these repairs will take place outside of normal construction hours.

The work has been scheduled to take place between Sunday, 15 July and Saturday, 28 July between 6pm and 6am.

Please see community notification for more information

 