Paving and tree grate replacement works – February 2020

Paving work will soon take place in the northern area of the foreshore walk, adjacent to Cirrus Dining. This work is being carried out to connect the old and new public areas together.

Works are expected to commence from Monday 17 February 2020 and will take approximately three months to complete. The work will take place during the approved construction hours of 7am to 7pm Monday to Friday and 7am to 5pm on Saturdays.

Works to replace all the tree grates on the foreshore walk are also expected to commence on Monday 17 February. This will take approximately three weeks to complete and will be undertaken in groups of 4 or 6 trees at a time. The work will take place during the approved construction hours of 7am to 7pm Monday to Friday and 7am to 5pm on Saturdays.

For more information and a map of the work, please read the community notification.